Norway’s 44in gas pipeline costs US$3.8M per mile, Guyana’s 12in gas pipeline to cost US$4.7M per mile

Kaieteur News – The world’s longest underwater natural gas pipeline is some, 725 miles long and was constructed at a cost of some US$2.8B or just about US$3.8M per mile for a pipeline that is about a meter in diameter.

The Langeled Pipeline delivers 26 billion cubic meters (900 billion cubic feet) of natural gas to the UK National Transmission System each year; the price tag came in at 1.7 billion pounds (US $2.8 billion).At the time of completion it was longest sub-sea pipeline ever built with a diameter of 44 inches. Guyanese were given an estimated cost for the pipeline during a media briefing held at the Arthur Chung Conference Centre, where the local head of the gas to energy taskforce, Winston Brassington disclosed that the offshore pipeline and riser are projected to cost some US$630M while the onshore pipeline will run from Crane West bank Demerara, to the Wales termination point would amount to some US$100M. Guyana is paying just about US$4.7M per mile for its 153 miles of pipelines, according to official figures touted by the gas to shore taskforce.


As such it would mean that Guyana is earmarked to pay about 25 percent more per mile than the amount it cost Norway to build Langeled, and for a pipeline that is, at 12 inches in diameter, significantly smaller.The Langeled Pipeline project included the construction of a new gas terminal at Nyhamna to process the gas coming from Ormen Lange. A consortium now exports natural gas from Nyhamna to Easington on the east coast of England through this state of the art marine pipeline.


Building the pipeline was said to come with immense technological challenges since the North Sea bed is not a flat bottom but is a treacherous series of channels, trenches, and ridges and it has cyclical plate tectonic events, not to mention a number of existing pipelines.It plunges to depths of 5 km (3.2 miles) making water pressure a significant factor in design and construction.As such, an autonomous underwater vehicle, Hugin, a product of Kongsberg Maritime, was employed to survey the sea bed, using advanced radar to determine the most cost effective route.


With an understanding of the features and hazards, design engineers went to work on plans to allow a 44 inch pipe, with 25mm (1 inch) thick walls, to negotiate the terrain while minimizing impact on fisheries and ecosystems.
In order to lay the pipeline a remote-controlled underwater excavating vehicle called the Nexan Spider, capable of moving underwater mountains, prepared the seabed floor.Three million tonnes of rock was brought to areas of the sea floor to level the terrain where needed.The pipeline was built using 100,000 pipe sections, each coated in asphalt to reduce corrosion and a stability coating of concrete.
Two pipe laying ships, including Soltaire, the largest pipe laying ship in the world, laid 8 km (2.5 miles) of pipe a day. Once the pipe was laid, deep water hyperbaric welding teams welded the pipes together from inside a watertight enclosure called Pipeline Repair Habitat.The project was completed in 2006 after three years of work and both Norway and the UK have benefited enormously from the project; the UK receives about 20% of its natural gas directly from the pipeline.


Meanwhile despite public consternation over the feasibility and environmental impacts related to the Guyana Project the Stabroek Block Operator has begun geotechnical and geophysical pipeline route surveys within Guyana’s Exclusive Economic Zone, along the Demerara River and off the Demerara Coast.
The survey area is approximately 12 nautical miles (22.2 kilometres) from the Coast of Guyana and covers an area of 457.4 square nautical miles (1568.9 square kilometres).This exercise is scheduled to conclude on October 15, 2021, and will incorporate the use of the OSV Cape Davis which will display the international signal for vessels engaged in such activities. MARAD had said this operation will incorporate the use of the vessels MV Wise Fox, MV Risen Star and MV Sealand Chirp, which will all be displaying the international signal for vessels engaged in such activities. The purpose of the surveys, is to inform the most ideal route for the proposed natural gas pipeline.


The massive project includes the construction and operation of a pipeline that will transport up to 50 million standard cubic feet per day (MSCFD) of dry gas from the Liza Phase One and Liza Phase Two Floating Production, Storage, and Offloading (FPSO) vessels to an onshore natural gas processing plant which will drop the pressure of the gas, dehydrate it, separate out propane, butane and pentanes +, and treat the gas to the specification to be received by a planned 200 Megawatt power plant.The project site lies approximately 23 km upriver on the west bank of the Demerara River on abandoned sugarcane fields. The project is expected to pave the way for a massive industrial park to be established at Wales which is expected to stretch across over 10,000 acres of land while the pipeline will terminate at Crane.


Exxon is currently conducting a number of public scoping meetings across Guyana ahead of the Environmental Impact Assessment study for the proposed gas-to-energy project.The EPA had previously anticipated that the project is expected to affect a vast portion of the surrounding environment in one but or another, and consequently requires an Environmental Impact Assessment to be done.

Replies sorted oldest to newest

Oil and Gas Pipeline Construction Costs

Source - https://www.gem.wiki/Oil_and_G...e_Construction_Costs

Summary

The following are ranges for pipeline cost estimates. For further discussion, see below:

  • Oil & Gas Journal 2015-2016: $4.75 million/km (US onshore gas)
  • Oil & Gas Journal 2014-2015: $3.23 million/km (US onshore gas)
  • American Petroleum Institute 2017: $3.32 million/km (US onshore gas, national average)
  • Global Fossil Infrastructure Tracker median for 64 onshore and offshore projects: $2.34 million/km (date unspecified, worldwide)

Background

There are four categories of pipeline construction costs; material, labor, miscellaneous, and right-of-way (ROW). The cost per category, expressed as a percentage of total construction costs, tends to vary by both location and year. Materials may include line pipe, pipe coating, and cathodic protection. Miscellaneous costs generally cover surveying, engineering, supervision, contingencies, telecommunications equipment, freight, taxes, allowances for funds used during construction (AFUDC), administration and overheads, and regulatory filing fees. ROW costs include obtaining rights-of-way and allowing for damages.[1]

Current Trends

Pipelines built in 2015 and 2016 were historically expensive, as determined by the costs for new projects as filed by operators with FERC, according to an Oil & Gas Journal analysis. For proposed onshore US gas pipeline projects in 2015-16, the average cost was $7.65 million/mile ($4.75 million/km), up from both the 2014-15 average cost of $5.2 million/mile ($3.23 million/km) and the 2013-14 average cost of $6.6 million/mile ($4.10 million/km). In 2012-13 the average cost was $4.1 million/mile ($2.55 million/km) as compared with $3.1 million/mile ($1.93 million/km) in 2011-12; $4.4 million/mile ($2.73 million/km) in 2010-11; $5.1 million/mile ($3.17 million/km) in 2009-10; and $3.7 million/mile ($2.30 million/km) in 2008-09.[1]

For the 33 land spreads filed for in 2015-16, cost-per-mile projections rose in all categories except material. In 2011 miscellaneous charges passed material to become the second most expensive cost category and they retained this position through 2016. Material-$992,991/mile, down from $1,012,698/mile 2014-15. Labor-$3,603,334/mile, up from $1,977,938/mile for 2014-15. Miscellaneous-$2,615,028/mile, up from $1,867,393/mile for 2014-15. ROW and damages-$441,548/mile, up from $378,255/mile for 2014-15. The continued rise in miscellaneous costs is driven by companies increasing the amount set aside for contingencies in their estimates.[1]

Labor spiked as a portion of land construction costs, reinforcing its place as the single most expensive category. Labor's portion of estimated costs for land pipelines jumped to 47.08% in 2016 from 37.77% in 2015, 42.36% in 2014, 38.84% in 2013, 44.61% in 2012, 44.27% in 2011, and 44.61% in 2010. Material costs for land pipelines, meanwhile, eased to 12.98% from 19.34% in 2015, 13.6% in 2014, 23.2% in 2013, 15.99% in 2012, and 14.54% in 2011.[1]

Average Pipeline Size

Pipeline cost is often estimated per inch-mile. According to NaturalGas.org, the average diameter of an interstate pipeline is between 24 inches and 36 inches, or an average of 30 inches.[2]

Offshore versus Onshore

According to USAID, offshore costs per mile for pipelines were about 1.96 times as high as costs per mile for onshore pipelines in 2000-2001, in 1995-1996 the cost ratio was 1.79.[3]

BTU Analytics Survey or U.S. Northeast and Central U.S. Pipelines

A survey by BTU analytics of 9 gas pipelines in the U.S. Northeast found a range of $5.5 million - $13.14 million per mile, with a median of $8.45 million/mile, or $5.25 million/km. The pipelines were onshore and ranged from 118 to 600 miles length. The pipelines were built from 2017 to 2020. The analysis also cited two pipelines in the Great Plaints and West Texas/Gulf Coast regions. Those pipelines included a pipeline built in 2009 that cost $2.98 million/mile in 2009 dollars, and two pipelines that cost $3.51 million and $5.15 million per mile respectively in 2019.[5]

Source & rest of article - https://www.gem.wiki/Oil_and_G...e_Construction_Costs

FM

Yeah DG, green water. How are the fires out there, they're easing up?  I don't hear much on it, must have become a way of life in that neck of the woods.

Summer in this neck of the woods is always being infiltrated by scantily clad women, no joke. The boats dock in town which is quite small, people step off dressed as they were onboard, ketch ma drift?  Some are VA VA vooommm...while some errr..let's say, the things I see when  I don't have my slingshot. The worse part, I can't unsee some of those 225 pounder wearing half a swimsuit because is like most of the bottom half stick up their backhatch, so to speak...you think I can ever unsee that stuff?

Sometimes is sheer horrors I tell ya.

cain

Hello Cain ...

The fires have toned down with some in various locations.

Bai Cain dem scantily clad women does create wonders.

In the hot weather here, dem women gat shart, shart clothes and happily displaying dem giggling bambalams.     

FM
Last edited by Former Member

Add Reply

×
×
×
×
×
Link copied to your clipboard.
×
×