Poor quality works done on schools under Region Four

-Auditor General’s report

Incomplete works at the Diamond Secondary School
Incomplete works at the Diamond Secondary School

Several schools built with funds from Region Four have shown severe defects according to the Auditor General’s report for 2022 which was laid in the National Assembly on  Monday.

The report said that a contract for construction of the Vryheid’s Lust South Nursery School was awarded on May 10, 2022 by the National Procurement and Tender Administration Board (NPTAB) in the sum of $31m.

The contract was signed on June 2nd 2022 with a start date of June 10, 2022 and a completion date of December 23, 2022. The full amount was paid to the contractor.

Source:

Replies sorted oldest to newest

@Mitwah posted:

Poor quality works done on schools under Region Four

-Auditor General’s report

Incomplete works at the Diamond Secondary School
Incomplete works at the Diamond Secondary School

Several schools built with funds from Region Four have shown severe defects according to the Auditor General’s report for 2022 which was laid in the National Assembly on  Monday.

The report said that a contract for construction of the Vryheid’s Lust South Nursery School was awarded on May 10, 2022 by the National Procurement and Tender Administration Board (NPTAB) in the sum of $31m.

The contract was signed on June 2nd 2022 with a start date of June 10, 2022 and a completion date of December 23, 2022. The full amount was paid to the contractor.

Source:

Ramaji, the AG said several schools built with funds from Region Four have shown severe defects. Shame.